Wind energy in Romania

More than 2.6 GW of new wind contracted under the CfD scheme, and an offshore framework in place.

In shortRomania's three CfD rounds awarded about 1.1 GW of wind in December 2024, roughly 1,260 MW in August 2025 at an average strike price of EUR 73.8/MWh, and about 316 MW in a wind-only round in December 2025. Onshore additions in 2025 were only about 330 MW, so the contracted pipeline represents a step change. Offshore, Law 121/2024 created the framework, and in 2026 the Ministry of Energy proposed three Black Sea perimeters totalling 3.1 GW towards a 3 GW target by 2035.

Key facts

· Data last reviewed 2026-09-14
  • ~330 MWof onshore wind installed in 20252026-01 · energynomics.ro
  • 2,514 MWnew generation and storage connected to the grid in 2026 (year to date)Photovoltaic 1,331 MW, storage 663 MW, wind 496 MW, hydrocarbons 20 MW, biogas 5 MW.2026-08-21 · Transelectrica
  • EUR 73.8/MWhaverage wind strike price in CfD round 2 (range EUR 65.17 to 79.5/MWh; ~1,260 MW awarded)2025-08 · Ministry of Energy; EBRD
  • ~316 MWof wind awarded in the wind-only CfD round 3, strike prices EUR 59.95 to 74.9/MWh2025-12 · Romania Insider; Renewables Now
  • 3.1 GWof Black Sea offshore wind proposed across three perimeters; national target 3 GW by 20352026-08 · Ministry of Energy (draft), Law 121/2024
  • ~24 GWwind and solar capacity targeted by 2035 in the Energy Strategy 2025-2035 (adopted November 2024); RES-E share target 58.5% by 20352024-11 · Ministry of Energy

Capacity awarded in Romania's CfD auctions

MW by technology and round

03727441,1161,488Round 1 (Dec 2024), Solar: 432 MW432Round 1 (Dec 2024), Wind: 1,100 MW1,100Round 1 (Dec 2024)Round 2 (Aug 2025), Solar: 1,488 MW1,488Round 2 (Aug 2025), Wind: 1,260 MW1,260Round 2 (Aug 2025)Round 3 (Dec 2025), Wind: 316 MW316Round 3 (Dec 2025)
View as table
ItemSolar (MW)Wind (MW)
Round 1 (Dec 2024)4321,100
Round 2 (Aug 2025)1,4881,260
Round 3 (Dec 2025)–316
Source: Ministry of Energy; EBRD; pv magazine; Renewables Now. Round 3 was wind-only.

CfD strike prices by round

EUR/MWh, average awarded price (range in table)

0.0018.0037.0055.0074.00Round 2 (Aug 2025), Solar: 40.46 EUR/MWh40.46Round 2 (Aug 2025), Wind: 73.80 EUR/MWh73.80Round 2 (Aug 2025)Round 3 (Dec 2025), Wind: 67.40 EUR/MWh67.40Round 3 (Dec 2025)
View as table
ItemSolar (EUR/MWh)Wind (EUR/MWh)
Round 2 (Aug 2025)40.4673.80
Round 3 (Dec 2025)–67.40
Source: Ministry of Energy; pv magazine (13 Aug 2025); Renewables Now. Round 3 shows the midpoint of the EUR 59.95 to 74.9/MWh range; the official average was not published in the sources used.

Onshore: from a stalled fleet to a contracted pipeline

Romania's onshore wind fleet, concentrated in Dobrogea, was largely built between 2010 and 2014 and then stalled; only about 330 MW was added in 2025. The CfD scheme changed the arithmetic. Round 1 awarded roughly 1.1 GW of wind across ten projects, round 2 awarded about 1,260 MW to 23 projects at strike prices between EUR 65.17 and 79.5/MWh, and the December 2025 wind-only round cleared about 316 MW at EUR 59.95 to 74.9/MWh. In 2026, 496 MW of wind was connected by 21 August, and the first CfD-backed wind farms moved into construction, several at once under the same developer.

Wind prices moved the opposite way to solar between rounds, rising rather than falling, because bidders would not go below the mid-sixties in euros per MWh. That is a signal about turbine, logistics and grid costs in Romania rather than about the resource, which is strong in the south-east and along the Black Sea coast.

Offshore: the Black Sea framework

Law 121/2024, adopted in May 2024, set the rules for concessioning offshore wind perimeters in Romania's Black Sea waters, and the World Bank published a roadmap for the sector in September 2024. In July and August 2026 the Ministry of Energy proposed three perimeters with a combined capacity of 3.1 GW (one of 1,900 MW and two of 600 MW each) as the first phase, and the government approved the rules governing the concession procedures. The Energy Strategy 2025-2035 targets 3 GW of offshore wind by 2035. No concession tender had been launched at the time of writing; the dates above describe the framework, not a project pipeline.

Grid, delivery and the 2028 deadline

Most CfD-awarded wind projects target 2028 for commercial operation, with a 36-month clock running from contract signature. Transelectrica's area-based capacity allocation, in force since June 2026, matters more for wind than for solar because the best resource is concentrated in a few counties where transmission capacity is already tight. The Romania-Bulgaria-Greece corridor and the new 400 kV Vulcănești-Chișinău line towards Moldova, energised in August 2026, add export routes for south-eastern wind output.

What this means for investors

  • Contracted wind (about 2.6 GW across three rounds) is the investable pipeline; offshore is a framework with proposed perimeters, not yet a tender.
  • Wind strike prices in the mid-sixties to mid-seventies in EUR/MWh reflect Romanian delivery costs; underwrite EPC and logistics accordingly.
  • Grid capacity in Dobrogea and Moldova regions is the gating factor; area-based allocation makes location part of the bid.
  • Onshore wind projects that missed the CfD rounds can still pursue PPAs and merchant routes, but with a different risk profile.

Momentum Energy's view

We see onshore wind as the segment where Romania's CfD design has done the most work, converting a decade of stagnation into a contracted pipeline. Offshore is worth tracking, but capital deployed today should be underwritten on onshore projects with a signed CfD and a confirmed connection. We treat the 3 GW by 2035 target as policy ambition until a tender is published.

The view above is Momentum Energy's opinion and is separated from the sourced facts in the tables. It is not investment advice.

Frequently asked questions

How much wind capacity has Romania awarded under the CfD scheme?

About 1.1 GW in round 1 (December 2024), roughly 1,260 MW in round 2 (August 2025) and about 316 MW in the wind-only round 3 (December 2025), together more than 2.6 GW.

What were the wind strike prices?

Round 2 wind cleared between EUR 65.17 and 79.5/MWh with an average of EUR 73.8/MWh; round 3 cleared between EUR 59.95 and 74.9/MWh.

Does Romania have offshore wind?

Not yet in operation. Law 121/2024 created the legal framework, the Ministry of Energy proposed three Black Sea perimeters totalling 3.1 GW in 2026, and the national target is 3 GW by 2035. A concession tender had not been launched at the time of writing.

Where is Romania's wind resource?

Mainly in Dobrogea (Constanța and Tulcea counties) and along the Black Sea coast, with additional potential in the eastern and southern plains. Grid capacity in these areas is the main constraint.