1.2 GW Approved, 1.07 GW Connected: How to Read Romania’s Biggest Solar Permit
Dama Solar is the largest solar farm in Europe at 1.24 GW DC, 1.07 GW connected and only 520 MW under CfD.

About 2.2 GW added in 2025 and 1,331 MW more in the first eight months of 2026.
In shortRomania is one of the fastest-growing solar markets in Central and Eastern Europe. Cumulative capacity passed 7 GW at the end of 2025, roughly half of it utility-scale, and 2026 connections are running ahead of every previous year. Revenue comes from 15-year Contracts for Difference (round-2 solar averaged EUR 40.46/MWh), corporate PPAs or merchant sales on OPCOM, and grid access is now allocated through a guaranteed capacity-allocation procedure.
Capacity connected to the Romanian grid in 2026, by technology
MW, 1 January to 21 August 2026
| Item | MW |
|---|---|
| Photovoltaic | 1,331 |
| Storage | 663 |
| Wind | 496 |
| Hydrocarbons | 20 |
| Biogas | 5 |
Prosumer capacity in Romania
MW installed
| Item | MW |
|---|---|
| Late 2025 | 3,350 |
| 31 May 2026 | 3,897 |
Romania installed about 2.2 GW of solar in 2025, taking cumulative capacity past 7 GW. The residential and commercial-and-industrial rooftop segments each hold close to 1.8 GW, and utility-scale plants account for roughly 3.5 GW. In 2026 the pace has continued: of the 2,514 MW of new capacity Transelectrica connected between January and 21 August, 1,331 MW was photovoltaic. Prosumers, who generate for their own use and inject the surplus, numbered 346,194 with 3,897 MW installed at the end of May 2026, and one in three of them now has a battery.
The largest projects have changed the definition of scale in the market. The biggest site announced and permitted to date, in Arad county, is planned at around 1 GW with co-located storage, and the first utility-scale hybrid sites have set the template for solar-plus-storage development. Individual projects and their developers are covered in our solar analyses.
Three routes coexist. The Contracts for Difference scheme gives 15-year two-way contracts: round 2 in August 2025 awarded 1,488 MW of solar at strike prices between EUR 35.50 and 45.20/MWh, an average of EUR 40.46/MWh, and round 1 had cleared solar at an average close to EUR 51/MWh. Corporate PPAs are the second route, with buyers increasingly asking for hourly matching evidence as CBAM reporting matures. The third route is merchant exposure to OPCOM's day-ahead market, which averaged EUR 150.51/MWh in January 2026 and EUR 109.56/MWh in May 2026, with sunny weekend hours already clearing below zero.
Those numbers describe a market where midday solar is abundant and evening power is scarce. Projects that can shift output, through co-located storage or a hybrid structure, capture more of the price curve than pure solar, which is why lenders and buyers now read hybrid designs as the bankability standard.
Grid capacity, not sunlight, decides which projects get built. Since 21 May 2026, Order 15/2026 of ANRE (Romanian Energy Regulatory Authority) requires a participation guarantee of EUR 20,000 per MW for capacity allocation requests, and Transelectrica allocates capacity by area through its updated procedure. CfD winners must reach commercial operation within 36 months, and most awarded projects target 2028, which concentrates EPC and equipment demand into a narrow window. Inverter procurement is also changing after the European Commission classified solar inverters as a cybersecurity-relevant asset for EU-funded projects.
Utility-scale projects are typically built on agricultural land outside built-up areas, whose sale follows the pre-emption procedure of Law 17/2014, or on land leased under superficies rights. In 2026 the government drafted a law to concession degraded agricultural land for renewable projects, which, if adopted, would open a new land route. Permitting runs through urbanism certificates, environmental screening, building permits and ANRE licensing; the sequence is well understood but the timelines vary by county.
Utility-scale solar in Romania is no longer an early-mover market, but it remains an under-built one relative to the grid capacity and demand growth ahead of it. We favour projects with guaranteed capacity, a credible EPC and a storage component, and we are cautious about CfD awards priced so low that forfeiting the bid bond could become the rational choice for the developer.
The view above is Momentum Energy's opinion and is separated from the sourced facts in the tables. It is not investment advice.
More than 7 GW at the end of 2025, after about 2.2 GW was added during the year, and a further 1,331 MW was connected between January and 21 August 2026 according to Transelectrica.
Round 2 (August 2025) awarded 1,488 MW of solar at an average of EUR 40.46/MWh, with bids between EUR 35.50 and 45.20/MWh. Round 1 (December 2024) awarded 432 MW of solar at higher prices, averaging around EUR 51/MWh.
Yes. Projects are normally held through a Romanian company. There are no sector-specific foreign ownership restrictions for generation assets; agricultural land transactions follow the pre-emption rules of Law 17/2014 and many projects use long-term land rights rather than purchase.
Negative hours already occur on sunny weekends with low demand. They mostly affect merchant revenue at midday and are one reason co-located storage and flexible PPAs are becoming standard.
Announced and permitted projects range from a few tens of megawatts to around 1 GW with co-located storage, the scale of the largest site in Arad county. Round-2 CfD solar awards alone covered 1,488 MW. Individual projects and their developers are covered in our solar analyses.

Dama Solar is the largest solar farm in Europe at 1.24 GW DC, 1.07 GW connected and only 520 MW under CfD.

Romania will reach 10 GW of solar early. Investors should now model the bigger opportunity: 26 GW of capacity in the 2040s.

Romania’s solar market beat every forecast. Here are three trends investors should watch during the second half of 2026.