R.Power Finishes Building Its 55 MWp Lazuri Solar Park in North-West Romania
R.Power's 55 MWp Lazuri solar park in Satu Mare is built but not yet live. What the CfD, the club deal and the licensing gap mean for investors.

Construction is complete at Lazuri, one of Romania’s largest solar farms by installed capacity, less than a year after work started on site. The plant is not yet energised: R.Power plans to switch it on by the end of 2026, under a 15-year contract for difference won in Romania’s 2024 auction.
On 16 October 2026, Warsaw-based independent power producer R.Power announced that construction works are complete at its 55 MWp (DC) Lazuri photovoltaic project in Satu Mare County, north-western Romania. The site has 88,708 PV modules and six medium-voltage stations, and the company is now preparing it for energisation and the start of commercial operation.
To be precise about the status: Lazuri is built, not live. Energisation is planned before the end of 2026. Until then, the plant sits in the gap every Romanian project has to cross between mechanical completion and a commercial operating licence, and that gap is worth understanding before anyone models a 2027 cash flow.
Lazuri at a glance
- Location: Lazuri commune, Satu Mare County, north-western Romania
- Installed capacity: 55 MWp (DC)
- Modules: 88,708 PV modules
- Medium-voltage stations: 6
- Grid connection: New 110 kV switching station, loop-in/loop-out on the existing Vetiș-Abator 110 kV line
- Expected output: About 70 GWh a year, equal to the consumption of more than 44,000 households
- Revenue support: 15-year contract for difference (CfD), Romania’s 2024 auction
- EPC contractor: NOMAD Electric
- Debt: Part of a €41.6 million club deal with ING Bank N.V. and UniCredit Bank S.A. (June 2026) for four PV projects of about 75 MWp
- Construction start: Late October 2025
- Construction completed: 16 October 2026
- Status: Completed; energisation planned by the end of 2026
Florin Federenciuc, R.Power’s country head for Romania, called completion “an important milestone for R.Power’s Romanian solar portfolio.” He added that the project had moved efficiently through development, financing and construction, and that Romania remains a key market in the company’s Central and Eastern European strategy.
From CfD award to finished site
The timeline is the part developers and lenders should study:
- Late 2024: R.Power wins 15-year CfDs for 85 MWp of solar capacity in Romania’s first CfD auction. Lazuri is the largest project in that group.
- July 2025: R.Power publishes the grid design, a new 110 kV switching station tapping the existing Vetiș-Abator line.
- Late October 2025: construction starts, with NOMAD Electric as EPC contractor.
- June 2026: R.Power signs a €41.6 million project finance facility (€34.1 million plus RON 39.5 million) with ING Bank N.V. and UniCredit Bank S.A., split equally on a club deal basis, for four PV projects totalling about 75 MWp, Lazuri included.
- 16 October 2026: construction complete.
- By the end of 2026: energisation planned.
Two details stand out. First, the debt was signed about eight months into construction, which means the early works were funded before the bank money arrived. Second, in June R.Power said the four financed projects were due to be connected in 2027. Lazuri is now aiming for energisation before the end of 2026, ahead of that guidance.
The numbers behind the headline
The following figures are Momentum Energy calculations based only on the disclosed data:
- Module size: 55 MWp over 88,708 modules is an average of about 620 Wp per module, in line with current utility-scale panels.
- Specific yield: 70 GWh / 55 MWp is about 1,270 kWh per kWp per year, a realistic figure for north-western Romania.
- Debt per MWp: €41.6 million across about 75 MWp is roughly €555,000 of debt per MWp. By capacity, Lazuri is about 73% of the financed portfolio.
- Currency mix: about 18% of the facility (RON 39.5 million, around €7.5 million) is a local-currency tranche alongside the euro debt.
- Strike-price sensitivity: at 70 GWh a year, every €1/MWh of CfD strike price is worth about €70,000 a year, or roughly €1 million over the 15-year contract. R.Power has not published the strike price for Lazuri.
Why the CfD makes this bankable
A two-sided CfD fixes the price the plant earns for 15 years. When the market price is below the strike, the generator receives the difference; when it is above, the generator pays the difference back. For a lender, that turns a merchant solar park into a contracted asset. It is the kind of revenue profile that lets two banks take a whole €41.6 million ticket in equal halves instead of building a wider syndicate.
With the price fixed, the risk that remains sits in two places a lender can check on site: the grid connection and the build. R.Power designed its own 110 kV switching station and used a single EPC contractor from first works to completion.
Between “completed” and “live”
Finishing construction is not the same as selling power. In Romania, a new plant needs Transelectrica’s conformity tests and final connection certificate, then a commercial operating licence from ANRE (Romanian Energy Regulatory Authority), then registration with a balancing responsible party (PRE). In July 2026, Transelectrica told Economica.net that 508 MW of finished capacity (229 MW solar, 97 MW wind and 182 MW storage) had passed its conformity tests but was switched off while it waited for those last steps. Market sources in the same report put the licensing step at between one week and two months.
For Lazuri, the date that matters for revenue is the commercial operation date, not the completion date. We will count it as live when it gets there.
R.Power in Romania
Lazuri is part of a Romanian solar, hybrid and storage pipeline that R.Power puts at about 1.5 GW. Separately, its 127 MW / 254 MWh Scornicești battery in Olt County is in the final phase of construction, with grid connection expected in late 2026 or early 2027.
Momentum Energy’s View
In June we asked how many of Romania’s CfD-awarded projects would actually reach commercial operation on time. Lazuri gives an early answer: under two years from auction win to finished site, and under twelve months from first works to completion. The template is simple: a CfD for price certainty, a small club of banks for the debt, and one EPC contractor carrying the design through to the end.
- Developers holding 2024 or 2025 CfDs: the binding constraint is no longer the auction. It is the grid connection and the licensing queue after mechanical completion. Put those weeks into your schedule and into your lenders’ base case.
- Lenders: a CfD-backed solar park with its own high-voltage connection is now a standard, financeable product in Romania. Two banks splitting €41.6 million equally shows that tickets of this size no longer need a syndicate.
- EPC contractors, including Turkish firms active in Romania: projects like Lazuri bundle a PV block with its own 110 kV substation. Teams that can deliver both under one contract are the ones CfD sponsors are looking for.
Lazuri is built. The next milestone, and the one that pays, is the day it starts selling power.
Sources and references
Organisations and documents cited in this article.
- Energy Global, 'Construction complete at R.Power's Lazuri solar project', 16 October 2026
- Romania Insider, 'R.Power completes construction of 55 MWp solar farm in northwestern Romania', 19 October 2026
- Renewable Energy Magazine, 'R.Power completes construction of 55MWp Lazuri solar project in Romania', 16 October 2026
- Energy Global, 'R.Power launches construction of 55 MWp solar park in Romania', 31 October 2025
- Balkan Green Energy News, 'R. Power Renewables to start construction of 55 MW PV project in Romania', 15 July 2025
- Economedia, 'Polonezii de la R.Power demarează construcția unui nou parc fotovoltaic în România', October 2025
- Gramwzielone.pl, 'R.Power rusza z budową farmy fotowoltaicznej w Rumunii', October 2025
- Romania Insider, 'Warsaw-based R.Power gets EUR 42 million for four PV projects in Romania', 24 June 2026
- PV Tech, 'R.Power secures finance for 75MWp Romanian PV portfolio', June 2026
- Energy Global, 'R.Power moves Romanian BESS into final phase of construction', 12 October 2026
- Economica.net, 'Instalații energetice noi, funcționale, de 500 MW stau oprite', 28 July 2026 (Transelectrica data as of 16 July 2026)
- Forbes România, 'R.Power finalizează lucrările de construcție la parcul fotovoltaic Lazuri', October 2026
- ANRE (Romanian Energy Regulatory Authority)
- Transelectrica (transmission system operator)